Staff recommended allowing smaller data facilities under size and location limits while prohibiting large data centers and campuses. Council members discussed noise, water and electricity use, fiber infrastructure and whether rules could keep pace with technology; the work session made no policy decision.
The full story
Chamblee staff recommended allowing smaller data facilities under specific limits while prohibiting large data centers and campuses, as the city considers rules before a 180-day moratorium expires Jan. 16. Planning and Development Director Matt Adams presented three options at the Nov. 12 work session; the council made no policy decision.
The options were to prohibit standalone data centers while allowing accessory server rooms, allow smaller facilities that meet size and impact limits, or allow data centers of all sizes under restrictions. Staff supported the second option, which Adams said could allow fiber-related facilities and smaller centers while excluding hyperscale developments. He recommended limiting them to industrial zoning rather than industrial-transitional areas and setting size and separation limits.
Adams described concerns raised in planning discussions about continuous cooling-system noise, generator emissions, electricity and water use, and site-design effects. He said some low-frequency sound may not be captured by standard decibel measurements. In response to a council question, he said some practices focus on low-frequency noise measurements rather than relying only on standard dBA readings.
Council members discussed whether a strict ban could be bypassed through variances. Adams said a prohibition written as a zoning-use restriction would not be eligible for a variance, while accessory server rooms would remain allowed. Another member described small fiber repeater facilities as necessary connection points for fiber service and said a broad ban could affect the network.
Adams said a recent DeKalb County land-use case involving four or five shipping-container-sized buildings, HVAC equipment and a backup generator helped prompt staff to consider regulation rather than a blanket ban. Council members also questioned potential employment benefits and the risks of splitting a large facility into smaller sites. Staff said it had no record of a request to locate an intermediate-line-amplifier hut in Chamblee before the current discussion, and the city’s existing code did not clearly anticipate data centers.