Highway work is expected to continue for four to five weeks, weather permitting, with chip-and-seal operations targeted to start June 9. The discussion also addressed road notices, last year's loose-stone complaints and contractor remobilization fees.
The full story
Decatur County's chip-and-seal work is targeted to start June 9, while wedge-and-overlay and skip-patching work is expected to resume Thursday after a contractor paused for a commitment in Rushville, according to the June 2 commissioners' meeting record. The three types of work were expected to continue for four to five weeks, depending on weather.