River Ridge drainage work targets July completion across four sites

Jun 23, 2026

All four drainage sites were under construction, with completion projected by the end of July if grading finishes. The work includes tree replacement and Oak Run pipe installation; unexpected coolant-line repairs and other added costs will be tracked against contingency.

The full story

Drainage improvements at four River Ridge sites were under construction on June 23, with the project expected to finish by the end of July if grading is completed, District Engineer Charlie Krebs told the River Ridge Community Development District Board of Supervisors.