Camas sewer plan outlines $270.3M capital program
Nov 17, 2026
Camas’ Planning Commission is scheduled to hear proposed updates to five facility plans, including a sewer plan with $270.3 million in recommended capital projects through 2045. The commission is being asked to recommend the plans to City Council for adoption.
The full story
The Camas Planning Commission is scheduled to hold a public hearing at 7 p.m. Nov. 17, 2026, on proposed updates to five school, sewer, water and transportation plans, then consider recommending them to City Council for adoption. A staff report says the updates are intended to align the plans with Our Camas 2045 and the city’s 20-year growth projections.
The largest spending plan is the city’s draft General Sewer Plan, which recommends a $270.3 million capital improvement program through 2045. The estimate is in 2025 dollars. The plan divides the spending into $132.4 million for the short-term period, 2027-2035, and $137.8 million for 2036-2045, with an average annual cost of $14.2 million over the 19-year planning horizon. The program includes treatment plant work, sewer pipes, lift stations and ongoing repair and replacement.
The sewer plan identifies capacity deficiencies in 10 localized pipeline areas and nine lift stations. Proposed work includes replacing or enlarging pipes, improving pump capacity and extending sewer service for planned development. The assessment is based on a hydraulic model that includes about 28% of the city’s gravity sewer pipes; the report recommends further model and system-data improvements. It also proposes investigating sources of stormwater and groundwater entering the sewer before some capacity projects are designed, to assess whether reducing that flow could reduce the need for construction.
The water system plan sets a 10-year improvement program and a 20-year planning framework through 2046. Recommended projects include well, reservoir, pump station and pipeline work. The plan identifies PFAS contamination as a concern and recommends continued monitoring and evaluation of treatment options. The city has begun treatment improvements at Well 13, and additional treatment at other wellfields may be needed.
The school plans describe different enrollment conditions within the city’s urban growth area. Evergreen School District projects declining enrollment through 2032 and says it will not collect school impact fees under its plan. Washougal School District’s plan anticipates near-term enrollment declines followed by stabilization and possible growth as housing is built; it projects enrollment could reach 3,250 by 2045. The transportation plan sets out a long-range framework for transportation needs and improvements through 2045.
The staff report’s recommendation is to “Hold a public hearing and forward a recommendation to City Council to adopt the proposed updates” to the five plans. The agenda lists remote participation by Zoom or phone and written public comments by email to [email protected], received up to one hour before the meeting. The public hearing is scheduled for 7 p.m. Nov. 17, 2026, in Council Chambers, 616 NE 4th Ave.