Hackensack expects street paving after July Fourth; project changes await vote

Jun 22, 2026

Street work is underway, with paving expected after the July Fourth holiday, weather permitting. Two project change orders, including removal of tree grates expected to save about $93,000 in grant-eligible costs, are scheduled for council consideration July 13.

The full story

Hackensack’s street construction is moving through removals and aggregate work, with paving expected after the July Fourth holiday, weather permitting, Moore Engineering’s Zach Thoma told the City Council on June 22. Curb and gutter installation was anticipated later that week, followed by sidewalks the next week.

Thoma said electrical work was also underway, with concrete bases being installed. He reported that the water-looping project had no outstanding punch-list items; closeout forms and lien waivers were being pursued for the July council meeting, and an 11-month warranty walk was scheduled before the end of August.

Linda MacNamara raised erosion and washout near Birchwood related to earlier project work. Thoma said he would contact Minnesota Department of Transportation project contacts Patrick and Emma and try to coordinate repairs with the contractor already mobilized in town. A second public hearing required by the Small Cities Development Program was also discussed, with Mayor Bill Kennedy suggesting it follow the July 13 regular meeting.

Thoma presented two change orders, one for each project contract, describing them as a way to shift work between contracts and maximize grant eligibility without changing unit prices. Removing tree grates because the trees would be planted in turf areas was expected to save about $93,000 within the grant-eligible budget; one gate valve was added to isolate a fire hydrant. The change orders were scheduled for formal consideration at the July 13 council meeting.