Butler County pool project change orders total $49,665

Nov 18, 2026

Butler County commissioners were scheduled to consider $49,665.63 in change orders for the SEBCO pool improvement project, including leak repairs, gas-line work and a replacement pool cover. An electrical contract extension tied to a permanent-power delay carried no added cost.

The full story

Butler County commissioners were scheduled to consider $49,665.63 in change orders for the Jefferson Township-SEBCO Pool Improvement Project on Nov. 18, including leak repairs, gas-line changes and a new pool cover, according to the agenda and attached change-order records.