Larimer County staff propose tiered review standards for data centers
Jun 29, 2026
Jun 29, 2026
County staff recommended definitions, power-demand thresholds, impact standards and monitoring requirements for possible data-center rules. Commissioners discussed the range of approaches, from strict review to prohibition, while staff prepares draft code and seeks a moratorium extension.
The full story
Larimer County staff recommended that any future data-center rules establish facility definitions, power-demand thresholds, review procedures and impact standards, while commissioners debated how restrictive the county should be. Staff said the existing moratorium ends Aug. 25 and planned to ask for a six-month extension at a July 13 land-use hearing; no extension or code changes were approved at the work session.