County reports bridge costs and approves juvenile center elevator change order
Nov 16, 2026
Nov 16, 2026
The county reported a $50,464 overrun on a completed Deer Creek bridge project and said a Westminster bridge in Arcadia was under construction. Commissioners also approved an $18,150 elevator change order at the Juvenile Justice Center.
The full story
Oklahoma County commissioners approved an $18,150 change order to resolve a conflict between an elevator control panel and a sewer line at the Juvenile Justice Center, and received updates on two bridge projects.