County building heating and cooling project nears system transition
Nov 5, 2026
Nov 5, 2026
The project presenter said courthouse heating and cooling work was progressing toward a phased transition, with the cooling tower work expected to wrap up by month’s end. The board also heard updates on other county buildings, thermostats and lighting.
The full story
Work on the county building’s heating and cooling system was progressing toward a phased transition, with the project presenter saying key installation work was expected to be completed by the end of the month. The first and second floors were largely complete, with branch boxes and basement work remaining before connections to the cooling tower area.