San Patricio County: Justice Center 61% complete; courthouse design work advances
Oct 6, 2025
County engineer gave a monthly update saying Fulton has received about $39 million to date on the Justice Center, the project is about 61% complete, and county staff are working with BRW on 50% design plans for the courthouse renovation.
The full story
John Hernandez, county engineer, told the San Patricio County Commissioners Court on Oct. 6 that work on the county’s new Justice Center is progressing and remains on the contractor’s critical path. “This month's payout is gonna be about … $2,700,000,” Hernandez said, and added that the county has paid Fulton approximately $39,000,000 so far and still has about $25,000,000 remaining to pay.