Contractor Robert Roberts LLC proposed value-engineering reductions that lowered the elections building estimate by about $1,070,166 and reduced the design footprint by about 6,200 square feet. Commissioners reported use of local subcontractors, ongoing geotechnical testing and further cost review with subcontractors.
The full story
The county’s elections building construction project is still under revision after contractor Robert Roberts LLC presented value-engineering measures that cut the estimated cost by about $1,070,166, commissioners heard Oct. 2.