Dispatch center construction progresses; managers cite weather delays and temporary systems planning
Summary
Contractor told supervisors the dispatch building had its first slab pour and crews are accelerating conduit work, roof deliveries and temporary heating/dehumidification planning to keep the project on schedule.
Construction representatives updated the Page County Board of Supervisors on progress and near-term work at the county’s dispatch facility, reporting the first slab pour in the dispatch and mechanical areas and ongoing exterior roofing and site deliveries. The representative said crews increased electrical crew size to complete underground conduit runs, poured a slab on the east side that includes dispatch…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat