Multnomah County and consultants present Sandy Boulevard plan; construction targeted for 2027

5788940 · September 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County consultants reported phase‑1 engagement, existing-conditions findings and two cross‑section concepts for Sandy Boulevard; planning to procure engineering for initial segment with construction likely in 2027 pending right-of-way and funding.

Multnomah County staff and consultants gave the Fairview City Council a status update on the Sandy Boulevard improvement project during the Sept. 17 meeting, summarizing community engagement findings and proposed design concepts for four corridor segments.

Why it matters: Sandy Boulevard is a major east‑west corridor with aging pavement, missing sidewalks and pedestrian‑safety concerns. The project aims to address roadway condition, pedestrian/bicycle facilities, drainage, and bus-stop access in staged construction.

Consultants reported roughly 400 survey responses in phase 1 outreach and extensive canvassing, tabling and interviews with schools, faith organizations, trucking representatives and homeowners’ associations. The survey’s top concerns were pavement condition, narrow/broken/missing sidewalks and pedestrian safety: “Getting hit by a car while walking or biking was one of the top three items of concern,” a presenter said.

Project plan: The corridor was divided into four segments (South Forest to Fairway Parkway; Ferry Parkway/Cliff Hollow area; Fairview Terrace and new apartments; industrial area toward Amazon). County staff and Alta Planning presented two cross-section options for constrained vs. wider right‑of‑way: Option A (sidewalk + raised bike lane) and Option B (sidewalk + multiuse path). The team will evaluate stormwater and culvert needs and coordinate closely with utilities and property driveways where rights-of-way are narrow.

Schedule and budget notes: Staff said they will seek an engineering contract to design the initial segment (the Hollow) in May 2026; engineering would take about a year, and construction is likely to be bid and start in 2027, subject to securing right‑of‑way and funding. Presenters said lighting and pedestrian-scale fixtures will be evaluated and a photometric analysis has already been completed during the existing‑conditions phase.

What’s next: The project begins round‑two outreach the week after the Sept. 17 meeting, and staff plan to return to the council in December with a more detailed draft plan after public feedback.