Sandstone asks Pine County to split $40,000 trail overrun after contractor underestimated work
5854434 · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
City and county previously agreed to split Sandstone Junction Trail costs; contractor found extra bituminous was needed and the city asks the county to split a remaining $40,000 overrun.
Sandstone city officials asked Pine County commissioners to share the cost of a $40,000 overrun on the recently completed Sandstone Junction Trail project, saying the contractor underestimated the amount of bituminous needed when bidding.
Kathy George, Sandstone administrator, told the board the trail project began in the 1990s with a small grant and partnership between the city and county.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans