MidAmerican says wind project roughly halfway built; components deliveries near completion

Sep 10, 2025

MidAmerican Energy told the Page County Board that turbine construction is about halfway complete, with 54 turbines planned and 22 erected though not yet commissioned; the company expects component deliveries to wind down within weeks and hopes to complete commissioning by year‑end.

The full story

A MidAmerican Energy representative gave the Board of Supervisors a construction update on the county wind project, saying the project is about half complete and that turbine deliveries and foundation work are winding down.