MidAmerican says wind project roughly halfway built; components deliveries near completion

5810779 · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

MidAmerican Energy told the Page County Board that turbine construction is about halfway complete, with 54 turbines planned and 22 erected though not yet commissioned; the company expects component deliveries to wind down within weeks and hopes to complete commissioning by year‑end.

A MidAmerican Energy representative gave the Board of Supervisors a construction update on the county wind project, saying the project is about half complete and that turbine deliveries and foundation work are winding down.

John Hovdeer, a MidAmerican Energy representative, told supervisors "There are 54 total wind turbines to be constructed. There are 22 that are completely constructed. Now they're not commissioned, so…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans