Board receives Liberty Elementary construction update, approves change orders
Aug 19, 2025
Administrators reported progress on Liberty Elementary construction (site work, retaining walls, building pad) and the board approved change orders including a $483,377.80 increase with Wright Construction and a $644,250 credit with Bloomsdale Excavating.
The full story
The Waynesville R-VI School District board heard a construction update on Liberty Elementary and approved multiple change orders for the project during the meeting.
Mister Harrison, staff member, showed site photographs and a phased schedule for Liberty Elementary, saying blasting for phase 1 is complete and that hauling and final grading will continue through October. He said Ryke Construction began work on footings for the building's Phase 2 and that observers should be able to see an above-ground structure by November, with a target substantial completion date around March 2027.
On formal actions, administration requested and the board approved change order number 2 with Wright Construction Services on Liberty Elementary Phase 2 in the amount of $483,377.80. Administration stated this change order "increas[es] the contract sum" to a total figure reported in the meeting record; the transcript included a garbled total for the new contract sum. The board later approved change order number 3 with Bloomsdale Excavating on Liberty Elementary Phase 1, a deductive change of $644,250 that district staff said reduced that contract sum to $11,312,136.09.
Harrison described the construction timeline: retaining walls were expected to be complete by February 2026; phase 1 excavating and site prep are nearing final grade; and the building contractor began digging footings at the time of the meeting. He also reported substantial completion of a separate high school HVAC project, with only balancing and punch-list items remaining.
Why it matters: The change orders adjust contract sums on a major capital project that will add an elementary school to the district. Administration provided a schedule linked to public visibility (structure visible around November) and a substantial-completion goal of March 2027.
Details and follow-up: Administration recommended and the board approved the change orders by voice vote. Staff said they will continue to report progress and punch-list activity for the high school HVAC project and the Liberty Elementary phases. Because the Wright Construction contract total reported in the meeting record appeared garbled, administrators should be asked to confirm the final contract sum for external reporting.
Written with AI from the event video and transcript. Check it against the source ↓
