Engineer: galvanized water-service replacements one-third complete; Franklin Field bleacher work progressing
Feb 5, 2025
Feb 5, 2025
Borough engineer reported the contractor has completed about 104 of 298 planned galvanized water-service replacements (approximately 33%) and that work is underway on field bleacher and streetscape projects.
The full story
The borough engineer reported Feb. 5 that the contractor on the galvanized water service line replacement project (Phase 3) has completed service replacements at 104 of 298 properties, roughly 33% of the total, and has started work on Third Avenue with an estimated one to two weeks to complete that street.