Measure EE update: Holly Glen TK conversion near completion; SLC relocation delayed by DSA back‑check
Summary
Wiseburn Unified staff and NAZ updated trustees on Measure EE bond projects on May 8, reporting that the Holly Glen TK conversion is about 75% complete and that the SLC future relocation project remains stalled while Division of the State Architect (DSA) back‑check comments are resolved.
Wiseburn Unified staff and NAZ program representatives updated trustees on Measure EE bond projects on May 8, reporting progress on multiple construction projects, contracts and approvals while flagging one permit delay and the complexity of pursuing federal IRA funding for energy projects.
Noemi of NAZ (Measure EE program representative) told the board that the Holly Glen Elementary TK conversion is roughly 75% complete and targeted for substantial completion on July 9 so rooms can be furnished over the summer. She said the project has required two change orders to date and that one recent change order adds classroom audio‑visual components and data drops that were omitted during the architect’s addendum process.
"We are roughly 75% complete," Noemi said. "This project started in January ... we're definitely on track for substantial completion on July 9, and we'll be able to start putting in furniture as soon as new furniture arrives." She explained that the AV/data work was omitted…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat