Jail construction on schedule; precast mockup and door hardware coordination planned

2964563 · April 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contract representatives said footings and foundation work are underway on the county jail, with roughly 300–400 linear feet of footing poured and a schedule-driven plan to sequence masonry walls and precast roof slabs. A detention door and hardware coordination meeting and a precast mockup are planned this week.

Jeff Curtis provided the board with a construction update on the ongoing county jail project, reporting that footings and foundation work are ongoing and that contractor Stickler Concrete has poured roughly 300–400 linear feet of footing.

Curtis said foundation walls are starting in the southeast corner and that the team plans to advance construction counterclockwise around the building so masonry bearing walls over the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans