Public Works updates Houston Bridge timeline; construction expected in 2026
Apr 1, 2025
Public Works staff told the Board the Houston Bridge project package is 60% complete and that the department has filed a CEQA notice of exemption; staff said federal emergency relief funding is being pursued and construction is tentatively expected in 2026 at an estimated $7 million cost.
The full story
Jim Henderson of Public Works provided an unscheduled appearance April 1 to update supervisors on the Houston Bridge. Henderson said Public Works is pursuing Federal Highway Administration emergency relief funding administered by Caltrans and that the project specifications and engineer’s estimate package are roughly 60% complete.