City approves final change orders on Watertown City Hall renovation; net decrease to construction contract

Summary

Council approved a decrease to the Hough Construction contract for the Wells Fargo/City Hall renovation and a small increase to the architect's professional services agreement for additional work during warranty/closeout.

The Watertown City Council approved two change orders on the city hall/Wells Fargo renovation on Aug. 18, including a net decrease to the prime construction contract and a small increase to the architectural services agreement. Item 9a: Hough Construction change order The council approved a change order with Hough Construction that reduced the contract by roughly $50,000, bringing the new contract amount to $4,204,558. City Manager Steger told the council that the building is largely complete and in the warranty phase; staff-initiated changes such as adjustments to the appliance package and door hardware produced overall cost reductions. Item 9b: TSP Inc. professional services amendment Council also approved Amendment No. 5 with architectural consultant TSP Inc. for additional construction services related to the city hall renovation. City Manager Steger said the amendment of about $7,300 addressed staff‑initiated changes involving duct work locations, electrical relocations and additional concrete footing work at the garage. The amendment raised the TSP contract to roughly $394,979. Discussion vs. decision Discussion only: brief staff explanation that changes were staff‑initiated and that the project is in warranty/closeout. Formal action: council voted to approve both change orders separately; motions carried on voice votes. Implementation and next steps City staff will continue warranty monitoring and follow up on open closeout items under the reduced construction contract and the amended architectural agreement. Financial details and clarifications - Hough Construction new contract amount: approximately $4,204,558 (net decrease of roughly $50,000). - TSP professional services total after Amendment No. 5: approximately $394,979 (increase of about $7,300).

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source