Bond program moves into permitting and elementary design phase; turf fields planned for 2025
Jun 9, 2025
District bond staff told the board that fields and grounds projects entered land‑use permitting, Pioneer Stadium pre‑application is pending, and elementary design advisory work is underway; staff estimated a 120‑day city land‑use process and said phase scheduling aims for construction across 2026–2027.
The full story
Bond program manager Mike Hobbs told the Oregon City School District Board that field and site projects are the earliest components to move into construction because their designs and permitting timelines are shorter, while elementary‑school design advisory work continues through the summer.