Board approves July pay application and hears jail-remodel progress report
Jul 25, 2025
Jul 25, 2025
Supervisors approved the contractor pay application covering work through July 1 and received a construction update showing progress on underground plumbing, electrical and precast/steel scheduling; staff noted a temporary budget variance and said June interest earnings should reduce the overrun.
The full story
The Osceola County Board of Supervisors approved a pay application for the county jail remodel covering work through July 1 and heard a detailed construction progress update from the project manager.