Airport master plan update: FAA reviewing development alternatives; chapter 5 expected soon

Jun 5, 2025

Board members heard that work on chapter 5 (development alternatives) of the airport master plan is underway, the FAA regional planner has reviewed preferred layouts, and staff expects a complete draft about eight weeks after chapter 5 is delivered.

The full story

Airport staff told the Aviation Advisory Board on June 4 that the airport master plan is in its final drafting stages and that the Federal Aviation Administration is reviewing the development alternatives presented at recent public open houses.