Court approves $351,700 amendment for Chambers Parkway design after pipeline conflicts force phase split

Jun 24, 2025

Commissioners approved a $351,700 amendment related to the Chambers Parkway project that added survey and project management work after the road design was split into two phases to avoid multiple pipeline conflicts; staff said the redesign reduced a potential $15 million pipeline relocation cost.

The full story

Chambers County Commissioners approved a $351,700 member request amendment for the Chambers Parkway Project to cover additional survey work and project management necessitated by splitting the project into two phases.