Authority hears update on cathodic protection work at Fall River piles; diving, anode work expected next week

Jun 27, 2025

Kavanaugh crews have installed anodes and completed knuckle welds at piles, but heat-related coating problems and tidal constraints have slowed work; diving operations and anode installations are scheduled to begin next week.

The full story

Kavanaugh, the contractor working on cathodic protection at Fall River piles, is advancing work but has faced coating, concrete-overspill and tidal challenges, the authority heard June 25.