County approves value‑engineering changes on behavioral care center, returns $266,863 to contingency
Jun 26, 2025
Jun 26, 2025
Oklahoma County commissioners approved seven value‑engineering items for the county's behavioral care center project, returning $266,863 to the project contingency and preserving planned quality, county staff said.
The full story
Oklahoma County commissioners on June 24 approved seven value‑engineering recommendations for the county's behavioral care center project, county engineering staff said, returning $266,863 to the project contingency.
