Lifetime Citizen Portal Access — AI Briefings, Alerts & Unlimited Follows
Board approves $839,789.03 pay estimate to Switlik and Sons for 2025 Street Construction Project B
Loading...
Summary
The board approved pay estimate number 2 for the 2025 Street Construction Project B (Fulton, First and Second streets) to Switlik and Sons for $839,789.03 following recommendation by project inspector Kurt DeBoer.
The Wausau Board of Public Works on June 24 approved pay estimate number 2 to Switlik and Sons for the 2025 Street Construction Project B, covering work on Fulton Street, First Street and Second Street, in the amount of $839,789.03.
Kurt DeBoer, the project inspector, reviewed the pay estimate and recommended approval. A board member moved to approve the payment; the motion was seconded and carried on an aye vote.
The payment was recorded as pay estimate number 2 for the project. No further substantive details were discussed publicly at the meeting.