Enbridge outlines progress, costs and scheduling risks for Utah pipeline replacement tracker

Jun 11, 2025

Enbridge Gas told the Utah Public Service Commission at a technical conference in docket 23-080-5718 that the company has replaced about 45% of the feeder-line footage listed on its tracker and has roughly 308 miles remaining, and described project timing, material choices and cost drivers for the 2024 annual plan.

The full story

Enbridge Gas told the Utah Public Service Commission at a technical conference in docket 23-080-5718 that the company has replaced about 45% of the feeder-line footage listed on its tracker and has roughly 308 miles remaining, and described project timing, material choices and cost drivers for the 2024 annual plan.