Capital projects team outlines summer 2025 work plan, flags EMS and deferred maintenance needs
Summary
Capital Projects staff presented the district’s summer 2025 schedule, including safety‑and‑comfort upgrades, synthetic field planning, fire alarm work at Meadowridge, and energy management system (EMS) upgrades; multiple consent agenda funding items were approved at the regular meeting.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Kent School District Capital Projects team presented a summer 2025 work plan on June 11 that identifies roofing, flooring, HVAC and controls upgrades, playground and parking projects, synthetic field planning and several deferred maintenance items.
The nut graf: Assistant Director of Capital Projects Brett Scribner said most projects will take place over the summer; several work orders required additional funding and were included on the consent agenda the Board later approved. Staff emphasized EMS (energy management system) upgrades that control HVAC and lighting and provide monitoring data for temperature, airflow and CO2; those controls are used to improve efficiency and operational monitoring.
Notable projects described: small‑site repairs (asphalt, trip‑hazard repairs), Kent Ridge High School D‑wing art remodel (annex/addition), Grass Lake sewer pump station repairs, Meadowridge fire alarm replacement (devices and new enunciator panel), Scenic Hill multimedia center bid and Meadowridge/other deferred maintenance items. Scribner showed a concept drawing for the Kent Ridge synthetic field (not the final plan) and noted several projects required additional funding because original budgets proved insufficient.
Board action: the Board approved consent agenda change orders and funding items tied to many capital projects at the June 11 meeting (consent items 11.02 through 11.22 were approved 4‑0, including EMS related work); a larger network cabling change order (11.01) was pulled for discussion and approved separately.
Operational context: staff noted capital projects and facilities teams coordinate with teaching and learning to minimize student disruption; some projects may have schedules that extend into the school year and staff will communicate impacts to sites ahead of time.
Ending: staff will continue to bid and schedule deferred maintenance work, complete Meadowridge fire alarm cutover, and pursue a staged plan for larger projects such as synthetic fields and media center construction.