Behavioral Care Center construction underway; GMP $44.4M and operator RFP to be released mid-2025

May 21, 2025

Flintco reported that construction of the Oklahoma County Behavioral Care Center began in January; the guaranteed maximum price is $44.4 million, the project has a July–October schedule for key milestones, and the county plans to issue an RFP for an operator with two advisory-board members appointed to the review committee.

The full story

Flintco told the Citizen's Oversight Advisory Board that work on the Oklahoma County Behavioral Care Center began in January and that major construction milestones are scheduled through 2026. "We've started the construction on the behavioral care center; broke ground in January," said Josh Patterson of Flintco during the update.