After a months-long feasibility study that found a marina could be cash-flow positive, the Cocoa Beach City Commission voted to close the consultant contract and to stop further planning and ballot placement following extensive public comment raising environmental, traffic and parking concerns.

The Cocoa Beach City Commission voted unanimously Tuesday to close out a consultant contract and to halt further progress toward building a municipal marina after hearing a feasibility presentation and more than an hour of public comment.

Edgewater Group, the marina consultant, presented a study that identified two possible sites — the Country Club shoreline and the hospital peninsula — and said a phased marina could be “immediately cash flow positive.” Brock Petrack, civil engineer with Edgewater Group, told commissioners the firm’s modeling showed strong market demand and that, depending on phasing and location, a marina could generate significant net operating income over time.

The study, the consultants and staff said, examined regulatory inputs including pre-application meetings with the U.S. Army Corps of Engineers, the Florida Department of Environmental Protection and Brevard County’s manatee protection plan. Edgewater cautioned that some permitting steps and shoreline work — in particular dredging and a wave attenuator at the hospital peninsula — would raise cost and lengthen permitting time.

Public commenters and several commissioners, however, raised environmental and traffic concerns and questioned the study’s assumptions. Blair Wiggins, who said he has led clam-restoration work in the Indian River Lagoon, warned that dredging and increased boat traffic could harm recovering seagrass and manatee habitat. Leonard Beckett, a longtime resident, challenged the study’s market comparisons and asked for examples of municipal marinas the firm has built and operated.

After public comment the commission voted 5-0 to accept the final invoice and close the consultant contract, and then voted 5-0 to stop progress toward building a marina or placing the measure on a future ballot. City staff were directed to remove the marina from the city’s short-term improvement plan.

Commissioners who supported halting the project repeatedly said they sought to give residents the final say rather than move forward administratively. At least one commissioner said the study showed feasibility but that extensive community concern meant the commission should not advance the project now.

City Manager Wayne Caragino and Stormwater Utility Manager Morgan Zuelke were present for the discussion; Edgewater’s presenters also answered technical questions about parking, dredging and manatee protections. Consultants said that some construction and soft costs were already budgeted in the firm’s estimate and that grant programs such as Clean Marina and federal boating grants could offset some infrastructure costs, but they warned those grants are not guaranteed and that independent technical and financial verification would be required before any design or permitting work proceeded.

Commissioners and staff also noted jurisdictional limits: the hospital peninsula site would require coordination with the property’s current owner and a complex permitting process before any city investment could proceed.

The commission’s action ends the consultant engagement after delivery of the study and directs staff not to pursue further design, permitting or public funding steps for a marina at this time. The commission indicated it would revisit the issue only if circumstances changed significantly— for example, if the hospital property were offered to the city for recreational use or if community sentiment shifted.

The commission’s votes followed a months-long engagement process that included a community survey, consultant fieldwork and the published feasibility report. Commissioners said they plan to preserve the public record of the study and the comments received so future decision-makers can reconsider the option if new evidence or conditions arise.