Authority approves $23,720 change order for airport lighting project; LEDs installed, PAPI delayed

3319863 · May 15, 2025

Summary

Board approved a $23,720 change order for the airfield electrical/lighting project. Airport staff said most runway lights have been converted to LEDs, a donated generator has been received, and PAPI components remain back-ordered.

The Hamilton County Airport Authority approved Change Order No. 1 for the airfield electrical and lighting project, adding $23,720 to the contract, mostly to cover nighttime paving and other material quantity differences.

A staff member giving the project update said, “The total amount for change order 1 is an addition of $23,720. 17,500 was due to the nighttime paving with the contract schedule changes.” The motion to approve the change order was moved and seconded and passed by voice vote.

Project status: Staff reported that the majority of runway lights have been converted to LEDs and that night closures for the project are complete. A few outstanding items remain: installation of PAPI lights for Runway 18 is still pending because components are back-ordered, finishing the electrical vault, and completing some south-hangar power transitions.

Generator and equipment: The airport obtained a generator from the county emergency management office; staff quipped about the cost, saying the airport paid “a dollar” to take the generator. The generator is onsite but not yet hooked up; staff said it will be connected once electrical work is finished.

Parking, AWOS and web services: North parking-lot paving was completed and striking is scheduled as weather allows. Staff reported intermittent problems with the AWOS phone line and that weather information that had been on a website is not yet visible online after a provider change.

Discussion: Board members asked for detail on the change order and percentage increase (staff said it’s “probably less than 2% of the total project”). Staff said they split the cost of a newly added exterior gate near the electrical vault 50/50 with the contractor to improve future access.

Decision: The board approved the $23,720 change order by voice vote.

Ending: Staff said electrical-subproject completion remains on the near-term schedule and that the authority will return with updates once PAPI components arrive and the FAA flight checks can be scheduled.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source