Board approves $20,604 change order for sanitary sewer lining project

May 6, 2025

Trustees approved change order No. 1 for the sanitary sewer lining project to add roughly 600 linear feet of lining at the contractor's bid price; funds are available in the project budget.

The full story

Village staff told trustees the low bid for the sanitary sewer lining project was favorable and the contractor agreed to honor the same unit price for approximately 600 additional feet of lining. The recommended change order No. 1 totals $20,604 and will increase the linear footage covered by the contract.