Assumption Parish staff seeks streamlined permit for Himalaya Canal work to avoid wetland mitigation

Jan 8, 2025

Parish engineers said they are pursuing a general programmatic permit for vegetation removal and limited excavation in the Himalaya Canal to keep impacts under one acre and avoid costly mitigation; work depends on state and U.S. Army Corps review.

The full story

Assumption Parish engineers told the Drainage Committee on Jan. 8 that removal of trees and debris from the Himalaya Canal will be scaled and staged so the work may qualify for a general programmatic permit rather than a full Section 404 permit that would require mitigation. Parish staff said they have been coordinating with the Louisiana Department of Natural Resources and the U.S. Army Corps of Engineers and were running final impact calculations to confirm whether the project could be reduced to less than one acre of wetland impact.