Nantucket pipeline construction progressing across multiple segments; several completion dates given
Mar 13, 2025
Mar 13, 2025
Larry Harris reported on the Nantucket pipeline: 98.6 miles total, 66.3 miles under construction, two pump stations under construction and multiple segment completion targets ranging from 2025 through 2029.
The full story
Larry Harris gave the Lake Atoka Reservation Authority a status update on the Nantucket pipeline corridor, describing multiple segments under construction, contractors currently working and expected completion windows.