Nantucket pipeline construction progressing across multiple segments; several completion dates given

2619597 · March 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Larry Harris reported on the Nantucket pipeline: 98.6 miles total, 66.3 miles under construction, two pump stations under construction and multiple segment completion targets ranging from 2025 through 2029.

Larry Harris gave the Lake Atoka Reservation Authority a status update on the Nantucket pipeline corridor, describing multiple segments under construction, contractors currently working and expected completion windows.

Harris said the pipeline program covers roughly 98.6 miles in nine separate projects, with about 66.3 miles currently under construction and two pump stations also under construction. He described segment-level progress: a pump station at the southern tip…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans