Public Works outlines ambitious 2025 construction program, timelines and right-of-way process
Summary
Public Works staff gave commissioners a line-by-line update on 2025 road, bridge and culvert projects, funding sources and the county’s right-of-way acquisition process, noting several active contracts and upcoming calls for bids.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
Public Works staff on Wednesday gave the Cowlitz County commissioners a detailed status update on 2025 construction projects, current bid timelines, funding sources and the county’s right-of-way acquisition process.
Susan (Public Works) and staff said three projects are under contract and in progress: water-line and pump-station work on Tower/Spirit Lake Highway; a contract-awarded guardrail repair run estimated at about $460,000; and an awarded Tootle wastewater treatment plant upgrade (about $1.45 million, ARPA-funded) that will appear on next week’s agenda for execution. A FEMA-funded Tang Creek culvert project is scheduled for a call for bids next week, staff said.
Public Works described its annual overlay (approximately $2.1 million in construction estimate) and said advertising depends on final WSDOT permits for work that affects state highways. Staff noted that CRAB (County Road Administration Board) RAP funds provide recurring biennial support (staff said the county typically receives between $1 million and $2 million per biennium) and that RAP distributions are based on county population and lane miles.
On larger projects, staff gave the board a detailed summary of the right-of-way process used for property acquisition: county appraisers prepare a valuation with comparable sales, the county offers compensation for permanent takes and temporary easements, and landowners can obtain and submit an independent appraisal (the county offers funds to pay for one) if they contest the amount. If negotiations fail, staff said eminent-domain proceedings are a last resort and require detailed documentation and separate board authorization.
Staff highlighted several projects and scheduling details to watch: advertising timing for South Cloverdale Road (delays caused by WSDOT specification changes and finalizing fish-handling requirements), Dyke Road (awaiting U.S. Army Corps of Engineers 408 permit and final utility relocations), Pleasant Hill bridge (temporary bridge in place; plan to construct much of the new bridge outside the water to minimize in‑water work), and a headwall repair on South Tootle Road for which staff proposed a short-term fix while pursuing grant funding for full replacement.
Staff also described the county’s temporary bridge inventory, noting some units are reusable and stored at the Castle Rock shop. Commissioners asked about insurance recoveries for guardrail damage; staff said the county bills motorists when an accident report is available but that many incidents have no report and therefore go uncollected.
No formal approvals were taken; staff asked for continued board readiness to sign routine documents (CRAB levy certification and other electronic signature delegations). Public Works said schedules remain subject to change and that some projects expected for 2025 may slip into later months.