The board approved a $135,258.07 pay application as part of the YMCA roof project; the county is acting as pass-through for grant reimbursement paperwork tied to a larger contract scope.

Decatur County commissioners on Feb. 3 approved a pay application of $135,258.07 (plus $0.71) related to the YMCA roof project.

County staff explained the commissioners serve as a pass-through for grant reimbursement: the YMCA submitted a reimbursement request for work on the roof, the county received and processed the application, and the board approved payment to move funds to the appropriate project account.

Why it matters: The payment advances construction reimbursement under the project—s grant and contract administration schedule.

Details: County staff provided the contract sum for the YMCA roof project ($1,276,900 as stated in meeting materials) and the pay application amount, which the board approved by motion.

Ending: County staff will process the payment through the grant reimbursement channel as the YMCA project advances.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source