Council authorizes engineering work for Brookmont Boulevard underpass repairs and sidewalks
Summary
The council approved an initial authorization to Pigash Engineering to survey and design repairs and sidewalks at the Brookmont Boulevard underpass, with staff estimating construction costs later by bid.
Get email alerts on the Infrastructure Brookmont topic
No spam. Unsubscribe anytime.
Kankakee City Council on Feb. 3 authorized Pigash Engineering to perform survey and preliminary engineering for the Brookmont Boulevard underpass, approving $98,326 now as the first phase of a $196,060 proposal.
City staff described the scope as survey and design work to repair retaining walls and railings that hold back soil and to add sidewalks on both sides from Washington Avenue to Schuyler Avenue. The proposal also includes streetscape lighting behind the concrete and repaving from curb to curb under the structure. Staff told council the bridge structure itself is sound but adjacent retaining walls and sidewalks require repair.
City staff estimated total construction costs at roughly $800,000–$900,000 pending bids. The council approved the resolution authorizing the engagement and noted the initial payment would come from capital funds. Staff said repaving, grinding and sewer utility checks would be included in subsequent construction scopes and bids.
Quotes and context
"There is no safety of that structure at this point of where that we're aware of of how it would fall or collapse or anything," a city official said, adding that retaining walls and sidewalks could fail over time and need repair. The official urged caution for drivers and pedestrians until work is complete.
The city indicated the project could proceed to construction in 2025 if bids and scheduling allow, but staff said 2026 is a realistic expectation for completion depending on bidding and contractor availability.
Implementation notes
Pigash’s full proposal lists $196,060 for engineering and construction management; the council allocated the survey and preliminary engineering portion now. Construction scope includes sidewalks on both sides, retaining-wall and railing repair, lighting and repaving; bids will determine final cost and schedule.