Council authorizes $460,604 additional funds for North Dixie Boulevard reconstruction
Summary
Odessa City Council approved a resolution to appropriate an additional $460,604.17 to cover the difference between the previously budgeted amount and the contract award for the North Dixie Boulevard pavement reconstruction project.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The City Council of Odessa unanimously authorized an additional $460,604.17 to cover the difference between the budgeted funds and the contract award for the North Dixie Boulevard pavement reconstruction project from Walnut Avenue to East 40th/46th Street.
Staff told council that on Nov. 26, 2024, the council awarded a bid to Reese Albert, Inc. in the amount of $1,982,104.17 for the North Dixie project. Council had previously appropriated ARPA funds for survey and design and earlier project costs; the award exceeded the budgeted amount by $460,604.17. The resolution approved by the council amended the city budget to appropriate additional funds from the general fund to the project account to cover the shortfall.
During council discussion a member asked whether there had been a problem with the bid process; staff replied the award was in order and the resolution was to formalize the appropriation not previously adopted by resolution. The council scheduled pre-construction meetings and voted to approve the supplemental appropriation so the project can proceed.
Council members asked few substantive follow-ups on the record. The motion to authorize the additional appropriation passed unanimously.