The Commissioners Court approved Change Order No. 11 for DLF2, Inc., adding 38 days to the Rantis County community building plaza/parking lot contract (GLO CDBG-DR contract 20-065-098-C270), moving the contract completion date to Feb. 28, 2025.

The full story

The Aransas County Commissioners Court voted to approve Change Order No. 11 for contractor DLF2, Inc., adding 38 calendar days to the construction schedule for the community building plaza and parking lot under the General Land Office Community Development Block Grant'Disaster Recovery (CDBG-DR) contract number 20-065-098-C270. The change order extends the contract completion date to Feb. 28, 2025.