Board hears plan for new Taylor training facility; boosters asked to raise $400,000
Jan 15, 2025
Jan 15, 2025
Superintendent presented an athletic training facility concept with an estimated cost of $1,330,640 and asked boosters to raise at least $400,000; the board agreed to form a subcommittee and said no construction will occur until design and funding are secured and final board approval is obtained.
The full story
Superintendent Dr. Allen outlined plans at the Jan. 14 meeting for a new athletic training facility adjacent to the existing Bayon practice area near East Miami River Road, telling the Three Rivers Local School District Board of Education the board and boosters have discussed the project for several years.