Contractor issues left 15% of Onalaska sidewalk project unfinished; replacement work completed this year

Jan 8, 2025

The board reviewed the status of a 2024 miscellaneous-concrete contract after BMD Concrete Innovations failed to finish the job. City staff solicited local contractors to complete most remaining work; about 85% of the project was completed and roughly 15% will be carried forward to 2025.

The full story

City staff told the Board of Public Works and Utilities that BMD Concrete Innovations, the prime contractor for the 2024 miscellaneous-concrete project, did not complete the contract by its October 2024 completion date and failed to return to finish scheduled work.