Board rejects two construction bids after code changes and bidding issues
Summary
The East Whittier City School District board rejected bids for restroom modernizations and the Emma Wicker Auditorium renovation, citing code changes and subcontractor prequalification concerns; both motions passed unanimously.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
The East Whittier City School District Board of Education unanimously rejected two recent construction bid packages at the meeting.
The board voted to reject all bids for BYR 25-25, the installation of portable restrooms at Lower Elementary, Mulberry Elementary and Orcharddale Elementary, after district staff said changes to code requirements from the Department of State Architecture (DSA) required additional fire-alarm work that was not part of the original bid scope.
The board also rejected all bids for BYR 25-26, the Emma Wicker Auditorium renovation project. District staff said the low responsive bidder faced two protests alleging subcontractor prequalification issues; staff recommended reissuing the bid and explicitly requiring subcontractor prequalification in the revised documents.
Both rejection motions were made and seconded and passed on unanimous voice/roll-call votes. District staff said rejecting the bids will allow the district to revise contract documents to reflect updated DSA code requirements and to require subcontractor prequalification so the projects can move forward without lingering bid protests.
Board members were told the re-bidding process should not materially delay the Emma Wicker project’s ultimate completion, though staff described the steps needed to ensure the projects comply with current code and procurement practices.