Monroe County accepts Justice Center schematic design, authorizes design‑development phase

5806440 · September 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission accepted schematic design for the proposed Justice Center and authorized DLZ and WGS to move into the design‑development phase; staff presented a proposed timeline targeting construction start in October 2026 and substantial completion in June 2029, subject to funding and legislative developments.

Monroe County commissioners voted unanimously Sept. 4 to accept the schematic design presented Aug. 29 for the proposed Justice Center and to authorize consultants DLZ and WGS to begin the design‑development phase.

Scott Carnegie, DLZ project manager, told the board that the typical design sequence is schematic design, design development and construction documents, followed by bidding and construction. Carnegie presented a timeline included in the schematic packet that anticipates a design‑development presentation in December 2025, construction‑document approval in June 2026, bidding in August 2026 and a construction start in October 2026 with substantial completion in June 2029, pending approvals and funding.

Commissioners expressed a desire to proceed despite ongoing budget and legislative discussions. Commissioner Madera said the move signals that the county is “moving ahead” and emphasized the need to send a clear message to the legislature that the project is advancing. Staff noted some state legislative matters remain unresolved that could affect the project, but the schematic acceptance allows consultants to continue design work.

The schematic materials and exhibits referenced in the Aug. 29 presentation are posted on the county website for public review. The board’s approval was by roll call; the motion passed 3‑0.