Contractor describes unexpected soils, engineering fixes as project schedule slips; seeks settlement to avoid litigation
Summary
Contractor EGS told the committee that unanticipated subsurface conditions discovered during excavation have delayed a major construction project and described engineering fixes and a revised completion target in May.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
Representatives for the contractor EGS told the committee handling Items 17 and 18 that unanticipated subsurface conditions discovered during excavation have delayed the project and triggered engineering solutions that have pushed back the contractor’s completion target.
The contractor’s representative said three categories of adverse soil conditions were found beginning in late January and that work in affected areas has paused while engineers devised remedies. He described planned fixes including the installation of rammed aggregate (concrete-filled) piers at portions of the site and helical piers and bridging where additional support is required. "We have an engineering solution," the representative said, and described a phased sequence: address the most critical areas, then resume work on the project’s critical path. He said resumption of critical-path work was expected within days and that the revised target for substantial completion moved from the end of the month to a date in May.
The contractor indicated it prefers to resolve outstanding costs and schedule impacts by settlement rather than litigation but said it is contractually obligated to continue work whether a settlement is reached or not. The contractor’s attorney was present and the representative noted counsel would likely press for settlement terms if needed. City staff and council members asked questions about the schedule impact, the technical approach and the expected ribbon-cutting timeline; Linda, a city representative, said a ribbon-cutting remains targeted for public works week in May based on where the project stood at the meeting.
On technical remedies, the contractor described rammed, concrete-filled piers (likened to a cross between stone columns and concrete piers) for former waste-transfer areas and helical piers — long screw-like elements drilled into the soil — for other building zones, plus bridging across existing foundations. The representative cautioned that each site condition is different and that the project team is coordinating engineering resources to avoid further schedule slippage. He said some non‑impacted site work continued at a lower workforce level while solutions were finalized.
No formal motions or votes were recorded on the record for settlement or contract modification during the portion of the meeting in the transcript; the discussion was framed as an update and an opportunity for the city and contractor to clarify technical approaches and scheduling. The contractor reiterated that, regardless of whether the parties settle outstanding claims, work will proceed under the existing contract obligations.