Council puts Skyway Gardens water‑pressure study back on workshop agenda after failed hydrant tests
Summary
Council discussed water‑pressure problems affecting the Skyway Gardens 2 development, reviewed a feasibility report from consultants and scheduled a water workshop (Oct. 7) with Jacob Martin to present options and cost estimates.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
City staff brought council an update on water‑pressure concerns tied to the Skyway Gardens 2 development and the consultant feasibility study by Jacob Martin, saying some pressure tests in the affected area have failed and further consultant input is needed to plan repairs.
Mike Macias of the water department summarized recent testing and the history of the problem: previous tests “barely passed” and later fire‑hydrant testing “failed,” he said. City staff noted Jacob Martin’s October 2024 feasibility comments that serving the lower hill from the existing pressure plane is not currently feasible and that a realignment and pressure‑plane adjustment would be required to increase pressure in the affected area.
Councillors said the matter likely requires substantial funding and detailed alternatives. Several council members requested Jacob Martin present options and estimated costs directly to council. The city manager and council agreed to invite Jacob Martin to the water workshop scheduled for October 7 at 4 p.m. so the council can review alternatives and cost estimates and determine next steps for budgeting and possible capital work.
No formal action was taken; council members asked staff to arrange the consultant presentation and to include Jacob Martin in the October workshop so the group can examine alternatives, timelines and budget implications in a longer session.