KDOT selects county bridge Y-13.7 for off-system program; commissioners authorize Cook, Flatt & Strobel design contract

5782863 · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A Chase County bridge on Y Road (bridge Y-13.7) was selected for Kansas Department of Transportation's off-system bridge program; commissioners approved moving forward with Cook, Flatt & Strobel for design work and executing required paperwork to meet KDOT deadlines.

Chase County learned Sept. 15 that bridge number Y-13.7 on Y Road, south of Glanville and north of Brad Colony, was selected for KDOT's off-system bridge program. County staff asked the commission to approve using special-bridge funds for the county match, to authorize an engineering agreement with Cook, Flatt & Strobel for design, and to complete KDOT paperwork by an Oct. 10 deadline.

The county engineer explained the project has a preliminary maximum funding allowance from KDOT of $1,100,000, and that the design contract with Cook, Flatt & Strobel is for $64,300. Staff noted the timeline: design work now, letting for construction no later than Sept. 30 of 2027, and construction likely in 2027 (with potential billing in 2028). The engineer described the site as a functionally obsolete, undersized bridge on a traveled farm-and-ranch route and said a temporary detour ("shoe fly") will likely be needed during construction because the available alternate route is a minimum-maintenance road.

The commission moved and seconded a motion to sign the agreement with Cook, Flatt & Strobel and to proceed with the KDOT forms; the motion carried by voice vote.

Why it matters: The project will replace a structurally or functionally deficient bridge, improve weight capacity for farm and ranch traffic and use a mix of KDOT funding and county special-bridge match dollars.

Next steps: Staff will finalize and submit required KDOT forms by Oct. 10, execute the design contract, and schedule follow-up approvals for construction-phase actions and budget timing.