Radio tower work progressing; one frequency and a change order remain outstanding
Summary
Committee received an update that radio tower construction has advanced to tower-climber work and equipment installation but still requires resolution of one frequency and an outstanding change order; December 15 switch-over target unchanged.
Get email alerts on the Radio Communications topic
No spam. Unsubscribe anytime.
County staff updated the committee on the radio tower project, reporting progress on tower climbers’ installation and one remaining frequency coordination issue.
Staff said climbers began installing equipment on the tower this week and that a significant change order will be forwarded to the full board; the executive and finance committee already received the change-order materials earlier in the week. Staff also explained certain microcomponents are delayed due to tariffs and supply issues, but the target switchover date remains Dec. 15. The update was informational and staff told the committee a project packet update is included in the executive and finance materials and will appear in the full board packet next week.
No formal action was taken; staff said they will continue to coordinate frequencies and finalize the change order for board consideration.