Clay County transportation program shows progress — and schedule disputes; some projects past contractual completion

5742139 · September 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff said several bonded road projects are underway but noted schedule disputes: one segment was 44% paid with 103% of contract time used and another showed 122% of time elapsed. County and contractors are negotiating time extensions; possible liquidated damages were discussed.

County staff gave the Board of County Commissioners an update Sept. 9 on bonded transportation and capital transportation projects, reporting steady field progress on multiple corridors but flagging schedule disputes and time-extension negotiations with contractors.

Warwick Sams, deputy director of Capital Projects, led the monthly update and listed work progress across the county’s bonded program. His briefing included pay-out and elapsed-time figures that prompted questions from commissioners: project pay-out percentages ranged from roughly half to nearly complete, while several contracts had used more calendar days than originally allotted.

Key status details reported by staff: - County Road 218 (Project 1): about 50.1% paid, 79% of scheduled time used. - County Road 209 (Project 2): about 59% paid, 41% of scheduled time used. - Project 3B (east connection through Sand Ridge/roundabout work): 44% paid, 103% of contract time used — staff said the contractor has requested additional days and the county is negotiating the appropriate revised schedule. - Cathedral Oak Parkway (project 6B): 99% paid, 122% of contract time used; listed as under contention by contractor. - As of Sept. 2, 2025, the bonded transportation program had expanded by $138,000,000 (program-wide expansion figure cited by staff).

Commissioners pressed staff for completion estimates and for clarity on the meaning of “103% of time used.” County officials explained that 103% indicates the contractor has exceeded the originally contracted number of calendar days; staff are negotiating extensions to determine how many of those days are compensable. Once a negotiated time extension is agreed, staff said the percent of contract days used will be updated and liquidated-damage assessments may apply if contractors exceed the newly negotiated schedule.

Kiewit and other contractors cited permitting, weather and site-start timing as reasons for time disputes, and county staff said each disputed schedule is being negotiated on a project-by-project basis. Commissioners asked staff to return with firm estimated completion dates and to follow up on liquidated damages where appropriate.

A separate petition from a business owner (hosted on change.org) asked for a change to a median design on one project; staff said they were working on a potential accommodation and would bring options back to the board if the change required a contract modification.

Why it matters: Bonded transportation projects account for major capital spending and local traffic impacts. Contractual schedule disputes can increase costs or delay safety and congestion relief measures.

What’s next: County staff will continue negotiating time extensions with contractors, provide updated completion estimates to the board on request, and report any negotiated contract amendments that affect schedule or cost.